Our Projects
Some of our most recent projects include: |
 |
Pendleton PFI, Salford - Affordable Housing Scheme
Cost-planning and risk management for Salford City Council’s £200M PFI regeneration scheme.
• Refurbishment of 1,250 existing council dwellings
• Construction of 800 new-build properties for social rent,
low-cost home ownership and private sale |
 |
Peel House, Pimlico - Social Housing Scheme
Construction of £15M redevelopment of the Victorian five-storey Metropolitan Police training centre in the heart of the City of Westminster.
• 70 affordable residential apartments
• Basement-level car parking
• 4 town houses |
 |
Other previous project experience includes: |
 |
Further Education College - Liverpool
Planning, funding and procurement for £35M, new-build three-storey learner centre.
• 10,000 sq m central learning resource for students
• IT suite
• Sports hall & gym facilities
• Recreational space
• Nursery facilities
|
 |
Further Education College - Merseyside
Construction project management of £4M new-build centre providing construction skills and training facilities for over 600 vocational students in a wide range of building trades.
• 1,500 sq m facility linked to the existing college
• Refurbishment of 3,500 sq m existing building and car park |
 |
Gateway 28 Distribution Centre - Derby
Construction of £13M, 24,000 sq m high-bay warehouse, manufacturing and distribution facility.
• Fire-protected with sprinkler system throughout
• Canopied delivery access and surfaced lorry park
• 2-storey, 700 sq m fully-fitted high quality office space |
 |
The Belfry Hotel - Warwickshire
Feasibility, design management, full environmental impact assessment and detailed planning application for £180M redevelopment scheme.
• 550-bedroom hotel and leisure complex
• New golf club house and driving range
• Sub-surface parking for 1500 cars
• New road access and internal landscaping |
 |
Head Office for Glass Manufacturing Company - Cheshire
Design and construction management of new UK head office.
• 2-storey 1500 sq m fully-fitted high quality office space
• Curtain walling glazing
• Fully air conditioned
• Testing and product quality assurance laboratory
|
 |
Glass Bottle Manufacturing Facility - Cheshire
Design, procurement and construction management of £280M new container glass manufacturing, filling and storage facility.
• Two 600 tonne gas-fired furnaces
• Production hall
• 50,000 sq m, 35m high-bay warehouse
• 20,000 sq m bottle-filling facility
. |
 |
London Underground Stations Refurbishment Programme
Project and health & safety management for Lift & Escalator replacement projects on the Bakerloo, Central & Victoria lines including extensive works at Marble Arch, Holborn, Marylebone and Bank underground stations. |
 |
Dungeness B Nuclear Power Station
Design coordination, safety case-management and planning for the installation of seismic modifications as part of a 10-year Periodic Safety Review for an operating 1200MW (AGR) Nuclear Power Station. |
 |
Jubilee Line Extension - London Bridge
Construction site management of new-running and station tunnels for NATM and permanent cast in-situ concrete lining works as part of the multi-billion pound extension to the Jubilee Line. |
 |
Thetford Power Station
Design & Construction of a 38.5MW power station, the largest chicken litter fuelled plant in the UK consuming 420,000 of litter per annum. |
 |
Concrete Gravity Base Storage Structure - Inverness
Design and construction of a pre-stressed reinforced concrete cellular tank with capacity to store up to 550,000 barrels of oil with concrete tower and a steel lattice drilling tower/conductor frame for the South Arne oil field in the north sea. |
 |
A406 North Circular Road Improvements
Construction site management for the installation of large diameter bored piles and deep-level diaphragm walling for the North Circular Road widening and new underpass scheme.
|